Progress Update: 15-02-2018

Progress Update: 15-02-2018

Following the completion of the Ground Floor Slabs, we began the works for the columns and elevator shaft. As at today, we have completed the columns and begun starting works towards the casting of the First Floor Slab works.

Casting Ground Floor

Casting Ground Floor

On the 26th of January, 2018 we started and completed the casting of the Ground Floor Slab. A full day of work but we pulled through it all.

Construction Update: January 20, 2018

Construction Update: January 20, 2018

Construction Works started in 2017, and we have been steadily going at it since then. The site required extensive and sturdy piling works for the kind of building we intend to place there. We had notable contractors who did the works on Piling and also the Pile Cap with Ground Beams. These have long been […]

Development Of The 59C Terraces & Penthouses

Development Of The 59C Terraces & Penthouses

You can see below the current 3D Imaging of the proposed Development of the 59C Terraces & Penthouses. More of the updates of this property will always be updated here. Stay Updated and kindly share.