Progress Update: 15-02-2018

Progress Update: 15-02-2018

Following the completion of the Ground Floor Slabs, we began the works for the columns and elevator shaft.

As at today, we have completed the columns and begun starting works towards the casting of the First Floor Slab works.

img

the59c

Related posts

Casting Ground Floor

On the 26th of January, 2018 we started and completed the casting of the Ground Floor Slab. A...