Construction Update: January 20, 2018

Construction Update: January 20, 2018

Construction Works started in 2017, and we have been steadily going at it since then. The site required extensive and sturdy piling works for the kind of building we intend to place there.

We had notable contractors who did the works on Piling and also the Pile Cap with Ground Beams. These have long been completed towards the ending of 2017.

Works are currently at the Ground Floor Slab stage, all preliminary works for the casting have been put in place and subsequently we will proceed with that.

We intend to start works on the columns almost immediately, and from there carry on to the pent floor with just the slabs and columns.

Block setting would be commence after the structure has reached its peak. We are also considering the innovation of dry-stacking here, as it has become a fairly common sight in modern developments.

I have included a few pictures illustrating the progress below.

img

the59c

Related posts

Progress Update: 15-02-2018

Following the completion of the Ground Floor Slabs, we began the works for the columns and elevator...

Continue reading
by the59c

Casting Ground Floor

On the 26th of January, 2018 we started and completed the casting of the Ground Floor Slab. A...

Continue reading
by the59c

Development Of The 59C Terraces & Penthouses

You can see below the current 3D Imaging of the proposed Development of the 59C Terraces &...

Continue reading
by the59c

Join The Discussion